The real cost of a machine hour adds what it costs to own and what it costs to run, divided by the hours it produces. Here we explain how to work it out step by step and with what data.

In short
  • The real hourly cost adds what it costs to own the machine, to use it and the operator, and divides it by the hours it really produces.
  • Dividing by engine hours is the most common mistake: idling and waiting don’t get paid.
  • The less the data depends on what someone writes down, the more reliable the result.

The formula

Cost per hour = (fixed costs + running costs + operator) ÷ productive hours.

It looks simple. The hard part isn’t the division: it’s getting the data that goes into it right. To do it now with your numbers, use the cost per hour calculator.

Fixed costs: you pay them even when it’s idle

  • Purchase or finance, spread over the years you’ll use it.
  • Loss of value: what it’s worth today minus what it’ll be worth when you sell it.
  • Insurance, taxes and permits.
  • Parking, storage and transport between sites, if not charged separately.

Running costs: they rise the more it works

  • Fuel: usually the biggest. Work it out per hour, per machine.
  • Preventive maintenance: oils, filters and services.
  • Repairs: breakdowns are that machine’s cost too.
  • Wear: tyres, tracks, blades and other parts that wear out.

The operator

Add their real cost to the business, not their net pay. If they don’t always use the same machine, split it by hours.

Which hours to use

This is where almost everyone goes wrong. A machine has three different hour figures:

HoursWhat they areWhat they’re for
EngineTime with the engine on, including idling.Planning maintenance.
ProductiveTime really working.Calculating real cost.
BillableThe ones you charge for.Knowing how much you leave uncharged.

If you divide by engine hours, the cost comes out lower than it is and your rate falls short. We explain it in how to track heavy machinery hours.

Mistakes that leave your rate too low

  • Using one average for the whole fleet: each machine has its own cost.
  • Leaving out idle hours: someone pays for them.
  • Forgetting breakdowns because they were “a one-off”.
  • Not updating it: fuel and parts change price, and machines age.
  • Working it out once a year from memory.

Where to get the data

With few machines, a well-kept Excel file works, if someone keeps it up to date. The problem comes when hours, refuelling and repairs are in different places and depend on what each person writes down.

What gives reliable data is recording it automatically: telematics provides hours and fuel, and a digital job sheet adds site, task and reason for stoppages. We cover it in what to measure with machinery telematics.

What to do with the result

  • Adjust the rate of each machine, with a margin that’s real.
  • Decide whether to repair or replace a machine whose cost keeps rising.
  • Tackle what weighs most: idle hours, idling or repeated breakdowns.

If you want that cost per machine and per site without chasing paper, see remote heavy machinery monitoring.

Sound familiar? See how we solve it in remote machinery monitoring or tell us about your case directly.

Tell us about your case↗

Questions,
on the table.

Which hours do I use to calculate cost per hour?

Productive hours. If you use engine hours, you count idling and waiting as work, and the cost comes out lower than it is.

How often should it be recalculated?

At least when something important changes: fuel, a big breakdown or how the machine is used. If the data records itself, it’s always up to date.

Should idle hours be included?

Yes. Fixed costs are paid even when the machine isn’t working, so they’re spread over the hours that do produce.